MIKE 11



C:\work\SOLProjects\11810549_HydroCast\TestModels\Karup\BaseModel\MIKE11\karup.sim11



Volume Balance Summary


A: Initial volume in model area         0.00 m^3
B: Final volume in model area         0.00 m^3
MIKE SHE overland inflow 273559.78 m^3        
MIKE SHE baseflow inflow 454374998.07 m^3        
MIKE SHE drain inflow 206062089.43 m^3        
Lateral sources inflow 0.00 m^3        
Lateral correction 413.02 m^3        
Open boundaries inflow 6493.27 m^3        
Rainfall runoff inflow 0.00 m^3        
C: Total inflow         660717553.56 m^3
MIKE SHE overland outflow     0.00 m^3    
MIKE SHE baseflow outflow     415.96 m^3    
MIKE SHE Drain outflow     0.00 m^3    
Lateral sinks outflow     0.00 m^3    
Open boundaries outflow     0.00 m^3    
Rainfall runoff outflow     0.00 m^3    
D: Total outflow         415.96 m^3
E: Continuity balance = B-A-C+D =         -660717137.59 m^3
Relative deficit E/max(A,B,C,D) =         -1.00 ()